Sunday 22 September 2013

Bradshaw Brook Sewer Repair 21 Sept 13

Went to see the works from the other side of the brook and see how they were getting to the work site.
Storage Compound 
 The mud slide from the storage compound to the work site.

 Although it has been graded the mud is more than 6 inches thick in places and very soft. 



and then you get there.
It will take nature quite some time to repair this mess.
The far concrete is now higher than in the pictures from earlier in the week which I did not expect, I thought that it was high enough before the increase. The bit with water on it is hopefully not going to be any higher as this is supposed to be low enough to allow fish move up river. 


More pictures when the work is finished hopefully next week.

No comments: